Abstract
Several simultaneously realized network projects of the PERT type with random works duration are considered. Every work consumes several resources types with fixed powers with all the resources being restored in the exploitation process. The directive fulfillment term and the allowable confidence probability of project accomplishment at the date are given for each project.